Plans move forward on Daniel Boone Missouri River bridge project

11:12 AM, Jul 10, 2012   |    comments
  • Share
  • Print
  • - A A A +

St. Louis (KSDK) - A contract has been awarded for a new I-64 bridge over the Missouri River.

The Missouri Highways and Transportation Commission released more details on plans for the project at its meeting this morning.

The project includes building a new I-64 bridge.  It will also provide a new bike and walking trail to connect the KATY trail to the Monarch Levee trail.

The budget for the project is $125 million.  But the commission awarded a contract to the lowest bid, which was $111 million.  The winning team is Walsh/Alberici.  The contractors hope to finish the project by December 2015, which is six months ahead of MODoT's deadline.

The new bridge will replace the current structure carrying westbound I-64 traffic from St. Louis County to St. Charles County.  The current bridge was built in 1935.